Community Meetings for Hydropower Development of Mathilo Sagu Khola Small Hydropower Project (10 MW)
The Aviyan Group, in collaboration with Alamphu Jalabidhyut Bikas Company Pvt. Ltd., has been actively engaging with local communities to facilitate the smooth progress of the Mathillo Sagu Khola Small Hydropower Project (10 MW). A series of community meetings have been held to address the concerns of locals, share project plans, and build consensus on key infrastructure development, including road access and camp facilities.
Meeting in Kyarthal Village
A pivotal meeting was conducted in Kyarthal village to discuss the construction of a road to the project's camp facilities. Local stakeholders, including community leaders, landowners, and technical experts, participated actively. The discussions revolved around road alignment, ensuring minimal disruption to local livelihoods and the environment. A consensus was reached on a tentative route, with locals expressing their support for the project, provided their concerns about fair compensation and environmental safeguards are addressed.
Engagement at Dhungakhani
A crucial meeting at Dhungakhani focused on strengthening collaboration and broader community engagement. Discussions addressed local grievances, employment opportunities, and fair practices during project implementation, fostering a spirit of cooperation and transparent communication between the company and the community. Following the meeting, the community gave consent to proceed with a detailed survey of the area, expressing strong support for the project's continuation. This marks a significant step toward building mutual trust and ensuring smooth progress in the development process.
Discussion and Introduction Program in Ward No. 6
The most recent meeting took place in Ward No. 6, where locals from Alamphu gathered alongside officials from Alamphu Jalabidhyut Bikas Company Pvt. Ltd. The program served as a platform to introduce the company's development plans and address local concerns.
During the discussion, officials detailed the timeline and scope of the hydropower projects, emphasizing the economic and infrastructural benefits to the region. Locals raised various issues, including equitable access to project benefits, employment opportunities for local youth, and support for community development initiatives. They also highlighted specific demands, such as improved road connectivity, water resource management, and measures to mitigate potential environmental impacts.
Detailed Design Phase Initiated
With the survey now completed, the Detailed Design Phase has been initiated. This critical stage encompasses designing layouts for key project components, including the powerhouse, headworks, and access infrastructure. The detailed design aims to align technical specifications with project requirements while addressing community and environmental considerations.